Completion Certificate
- After completing the construction, the owner(s) through Architect shall intimate DDA/MCD. The Architect shall certify that the construction has been carried out as per the proposal submitted earlier and is in conformity with building bye-laws and guidelines for addition(s)/alteration(s) in DDA flats.
- The intimation of completion shall have to be given within 3 years of submission of plans for addition(s) / alteration(s) to DDA/MCD. If no intimation regarding completion of construction is received within 3 years, the permission granted will automatically get revoked and withdrawn.
- In cases where construction has already been carried out and only regularization is required, there will be no need of completion certificate.
|
|
|
|
|
|
|
|
|